PROJECTS
Dutch method for installation pre-fab concrete piles below excavation levels: the vibro combination
2018-01-30    by : Arjen
  • Dutch method for installation pre-fab concrete piles below excavation levels: the vibro combination
  • Dutch method for installation pre-fab concrete piles below excavation levels: the vibro combination

Precast Concrete foundation piles are often driven from the surface level and then cut at the required depth after excavation of the construction pit. The excavation depth is dependent on the type of project, typically decided by underground levels for parking. This can lead to the waste of each pile of up to 10 meters. Reducing this waste does not only reduce material and installation cost, but also requires shorter pile lengths to be transported by truck.


ICE,precast concrete pile,vibro compaction pile,impact hammer

 

In Holland the following method is a popular solution to this problem:

1. Install a retaining wall, preferably with sheet piles or combi-wall; alternatively an SMW or diaphragm wall can be chosen


ICE,precast concrete pile,vibro compaction pile,impact hammer
 

2. Set up a steel casing with detachable base plate at ground level.

3. Drive the now closed bottom steel casing into the soil, the length of the casing should be length of pre-cast pile + excavation depth. During driving the pile, the soil is displaced and improved

 

ICE,precast concrete pile,vibro compaction pile,impact hammer
 

4. Check to see if the tube is dry and clean

5. Lift a pre-fabricated, pre-stressed concrete pile with head reinforcement and possibly ridges for connection to a concrete floor into the casing
 

ICE,precast concrete pile,vibro compaction pile,impact hammer
 

6. Pour grout into the casing to fill around the pile over the length of the bearing soil layers to improve shaft friction. Once the space between the casing and pile is filled the steel tube is ready to be withdrawn
 

ICE,precast concrete pile,vibro compaction pile,impact hammer

 

7. Extract the casing by vibratory hammer, the casing is now ready to be used again

8. Excavate the construction pit by excavator or sand pump

9. Pour a concrete floor onto the floor of the pit

 

The method is suitable for complicated soil profiles and softer soils, especially those in a river delta like Shanghai.


ICE,precast concrete pile,vibro compaction pile,impact hammer
 

The advantages are:

Suitable for a wide range of pile diameter designs 

Soil improvement achieved as the vibro-combination pile is a soil displacement method

No risk of pile damage pre-stressed concrete piles in case of heavy piling works

Saving pile length, no pile cutting needed

Easier transport of (shorter) piles in city center

No bentonite is needed, no soil is excavated

Best solution for very weak deeper soil layers where creating a cast-in-situ pile shaft is impossible


More information about the pile:

Precast concrete piles have a large tensile force combined with the rougher wall and larger cross-section of a vibro pile, thus enhancing the tensile performance through soil friction. This type of pile is often ribbed at the top to connect well with the floor that is to be poured. The system is used for tunnels and basements, often together with an underwater concrete floor. 


Recommended equipment:

1. DRIVING: ICE Impact hammer, a noise-reducing shroud may be fitted.

2. EXTRACTING: ICE Resonance Free vibratory hammer

3. PR-90 piling rig for accurate pile positioning and high-output pile production


Special aspects

Pre-drilling preceding the production process could considerably reduce driving time.

Sound reductions can be realized during the production process whenever a sound shield is applied.

 



Questions that
need to be answered?
I would be happy to answer them personally to you
Julie Zhao
Sales Support Manager
Ask your question
021-34688990
  • Shanghai ICE Construction Machinery
  • Phone: (86) 21 3468 8990
  • Fax:  (86) 21 3468 8901
  • Email: contact@icevibro.com
  • Website: www.icevibro.com
  • Address: 6999 ChuanSha Road,
  •      PuDong District,No.B8,
  •      201202 Shanghai,China

沪公网安备 31011502008669号


沪ICP备19006476号